Earned value method in construction

The earned value method in construction project management

The earned value method is the system of the techniques used for measurement and control of efficiency of project performance. The method is based on the analysis of a number of numerical indicators calculated in the process of project implementation.

Constant monitoring of the earned value and other indicators allows the project manager to predict the success of its completion on schedule, the risks of exceeding these deadlines, budget overruns and so on.

 

The method operates with the following indicators:

 

Indicator

Description

Formula

Name of the Indicator in Project map

PV

Work volume scheduled to complete for reporting date

PC * scheduled completion %

BCWS 

Budgeted cost of work scheduled

AC

Actual / earned cost of work for reporting date

AC * actual completion % 

ACWP

Actual cost of work performed

EV

Earned value

 

The actually completed value of work indicated in the budget.

 

In other words, the real (actual) cost of work performed in accordance with the plan at the reporting date

BAC * actual completion % 

BCWP

Budgeted cost of work already completed at the reporting date

BAC


 

Budget at completion (BAC)

The whole budget for the entire project - the budgeted cost of the project

Sum of all budgets of all works

BC

Budgeted cost

CV 

Cost variance

BCWP - ACWP

(CV = EV - AC)

CV

Cost variance

BV

Budget variance

BCV = BC - AC

BCV

Variance between Budgeted and Actual cost

CPI

Cost performance index

BCWP / ACWP

(CPI = EV / AC)

CPI

Cost performance index

SV

Schedule variance


 

SV = BCWP - BCWS

SV

Schedule variance

SPI

Schedule performance index

 

How far have we deviated from the plan

BCWP / BCWS 

(SPI = EV / PV)

SPI

 

Schedule performance index

EAC

Estimation at completion

What will be the budget upon completion of the project

EAC = BAC / CPI

EAC

Estimation at completion

VAC

Variance at completion

VAC = BAC - EAC

VAC

Variance at completion

ETC

Estimation to completion

How much is left to complete the work

ETC = EAC - AC

ETC

Estimation to completion

 

Let's take a look at the example of applying earned value method to our project:

 

The table contains a list of project tasks, their costs and duration:


 

#

Work

Predecessors

Planned duration, days

Budgeted cost, per day

Budgeted cost, total

1 A   2 100 200
2 B A 2 150 300
3 C B 2 120 240
4 D B 3 200 600
5 E D 2 200 400
6 F   3 100 300
7 G   4 25 100

 

This is how it looks on the network diagram (Gantt chart)

Yellow lines - baseline plan

Blue lines - actual plan

 

Suppose we received data from the project manager from field about the completion of tasks for the reporting date:


 

#

Work

Actual completion, %

Budget variance

1 A 100 -160
2 B 100 -60
3 C 50 0
4 D 10 -80
5 E 0 -100
6 F 20 60
7 G 80 0

 

Let's supplement the data with actual indicators:

For date: May, 17

#

Work

Predecessors

Planned duration, days

Budgeted cost, per day

Budgeted cost, total

Actual duration, days

Actual cost, per day

Actual cost, total

  PROJECT   9   2140 10   2480
1 A   2 100 200 3 120 360
2 B A 2 150 300 2 180 360
3 C B 2 120 240 2 120 240
4 D B 3 200 600 3 220 680
5 E D 2 200 400 2 250 500
6 F   3 100 300 3 80 240
7 G   4 25 100 4 25 100

 

As you can see from the report, the real situation is slightly different from the plan.

Using the formulas above, let's calculate the development rates.

Indicators of project development:

#

Work

BCWS

BCWP

ACWP

CV

CPI

SV

SPI

EAC

VAC

ETC

  PROJECT 1643 1330 1584 -254 84% -313 81% 2549 -409 965
1 A 200 200 360 -160 55.6% 0 100% 360 -160 0
2 B 300 300 360 -60 83% 0 100% 360 -60 0
3 C 240 120 120 0 100% -120 50% 240 0 120
4 D 556 480 544 -64 88% -76 85% 680 -80 136
5 E 0 0 0 0 0% 0 0% 0 0 0
6 F 278 150 120 30 125% -128 53% 240 60 120
7 G 69,5 80 80 0 100% -10.5 114% 100 0 20

 

 

For the whole project :

 

CV = BCWP - ACWP

1330 - 1584 = -254

 

CPI = BCWP / ACWP

1330 / 1584 = 0.84

 

SV = BCWP - BCWS

1330 - 1643 = -313

 

SPI = BCWP / BCWS 

1330 / 1643 = 0.81

 

EAC = BAC / CPI

2140 / 0.84 = 2548

 

VAC = BAC - EAC

2140 - 2548 = -408

 

ETC = EAC - ACWP

2548 - 1584 = 964

 

Estimated duration of the project:

EDP = Planned duration / SPI

9 / 0,81 = 12 days (round up).

We can assume that with such a speed of development, the project will be completed in 12 days. 

Based on the above received development rates, we can estimate the condition of our project

 

 

SV < 0

SPI < 1

SV > 0

SPI > 1

CV > 0

CPI > 1

Saving the budget

Lagging behind the schedule

Saving the budget

Ahead of schedule

CV < 0

CPI < 1

Overspending the budget

Lagging behind the schedule

Overspending the budget

Ahead of schedule

 

Let us explain this scheme.

The positive value of the indicator CV (Cost variance) tells us that we are saving money. 

And negative - that we are overspending.

The negative value of the indicator SPI (Schedule performance index) tells us that we are working slowly and behind the scheduled terms. We should speed up.

A positive indicator value - we are keeping up with the schedule.

The time and cost indices tell us how far behind schedule and budget we are.

If the values ​​are less than one (less than 100%), then the situation is unfavorable. Otherwise, we keep up with the schedule and budget.

The earned value method described above is implemented in the Project map construction project management system.

In the Project map, you can easily analyze your project, track the actual development rates, as there are all the necessary tools for this.

The resulting analytical reports of development can be saved for later analysis. You can always refer to the archive of reports to analyze the progress of changes in the project.

With our project management system, you can competently manage and analyze projects. Project map will help the project manager to identify problem areas in time and make the right decision in advance, where to accelerate work in order to keep up with the schedule, and where to increase funding or reallocate resources to minimize risks.

Report example:

Use modern and efficient project management tools

Start scheduling